The Devils in the Detail
Handover inspections aren't just only about paintwork. One of the most common reoccurring defects we find where builders get it wrong is detailing of waterproofing on bathroom and ensuite cavity sliding door openings. The Australian Standard 3740 – 2010 Section 3.9.1.2 requires the perimeter on the classified wet area to be sealed and waterproofed. Too often we find the aluminium water stop finishing in the cavity and not returning across the bottom of the door jamb, not


Safety Hazard Foil Insulation
The governments Insulation Scheme has left multiple homes where safety hazards may exist in ceilings. Insulation is required to be checked by an electrician and a clearance / safety certificate issued. In our normal working conditions we find many homes have gone unchecked since the scheme was cancelled. The foil is laid over the joists and if it comes in contact with metal or existing wiring it can become live through incorrect installation, putting home owners or workers